A summary and a monthly timeline of our Koi Pond project from start till finish...

Never the Idle Dreamers

May 2010 - Clearing the area

Never the Idle Dreamers

June 2010 - Construction of first raised bed and pathway begins

Never the Idle Dreamers

July 2010 - the Big Dig has begun

Never the Idle Dreamers

August 2010 - the dig continues and first raised bed fills up with the spoil from the dig

Never the Idle Dreamers

September 2010 - hand digging continues and seating area ground level rises up

Never the Idle Dreamers

October 2010 - first raised bed filled up and levelled

Never the Idle Dreamers

November 2010 - winter pause and pond build becomes static

Never the Idle Dreamers

January 2011 - planning for the finishing touches and equipment needed

Never the Idle Dreamers

February 2011 - pond build recommences and installation of new fencing begins

Never the Idle Dreamers

March 2011 - hand digging continues and second raised bed fills up

Never the Idle Dreamers

April 2011 - new fences and trellis are up and yes, hand digging continues

Never the Idle Dreamers

May 2011 - planting of the first raised bed begins

Never the Idle Dreamers

June 2011 - coping stones on the first raised bed

Never the Idle Dreamers

July 2011 - build of the pond wall commences

Never the Idle Dreamers

August 2011 - pond wall build continues

Never the Idle Dreamers

September 2011 - bottom drains and main pipe works installed 

Never the Idle Dreamers

October 2011 - pond wall goes up and up...

Never the Idle Dreamers

November 2011 - construction of the filter house begins

Never the Idle Dreamers

December 2011 - construction of the third raised bed and water feature begins

Never the Idle Dreamers

January 2012 - third raised bed and water feature completed and rendered

Never the Idle Dreamers

February 2012 - fence painting has begun

Never the Idle Dreamers

March 2012 - planting of the second raised bed begins

Never the Idle Dreamers

April 2012 - skimmer line and return pipes installed, work on filter house continues

Never the Idle Dreamers

May 2012 - final height of block wall attained and pond window frame measured to fit

Never the Idle Dreamers

June 2012 - construction of pergola begins

Never the Idle Dreamers

July 2012 - painting of the pergola begins

Never the Idle Dreamers

August 2012 - insulation on pond walls applied ready for fiberglassing

Never the Idle Dreamers

September 2012 - fiberglassing completed and pond now water tight

Never the Idle Dreamers

October 2012 - landscaping continues, pathway finished off

Never the Idle Dreamers

November 2012 - filter equipment assembled

Never the Idle Dreamers

December 2012 - thorough cleaning and disinfection of the pond in preparation for filling up

Never the Idle Dreamers

January 2013 - construction of the decking begins

Never the Idle Dreamers

February 2013 - small water feature finished and running

Never the Idle Dreamers

March 2013 - pond window installed and sealed

Never the Idle Dreamers

April 2013 - pond filled up, fish introduced, system all running. The pond build has finished

One of the comments we received before that now holds a special place in my consciousness is that we are 'never the idle dreamers'. As I gathered these photos and looked back at what we have done it reminded me how much hard work we have put in to achieve what we have now. And it's something we are so proud of!

We wanted something, we did the work ourselves, and now we're enjoying it. But what makes this sense of enjoyment extra sweet is that we worked hard for it.


Never the idle dreamers!


And pond reveal coming up soon!


Mark :-)