I got word a week or so ago that our cee purlins are on the way from Phoenix, but it’s a route truck so it’ll probably be another week or two before they actually arrive. The roof panel order took longer than I anticipated to process, but they finally charged my credit card last Friday; I then got an email telling me they weren’t able to deliver here, but we could pick the panels up ourselves from the plant…which is in Kent (suburban Seattle). Now, I have no idea why we couln’t find this place when we were searching for local suppliers; the office we dealt with is in Tennessee. But at least I’ll get a refund on my shipping fee, and it’s no big deal to send Chekhov to Seattle with the trailer. A couple of days ago we shifted the steel tubing into Grace’s shop, so she’ll be starting on the trusses next week; since the shop is enclosed she’ll be able to work regardless of rain (which we’ve had quite a lot of lately), and we’ll only need to work around the weather to actually get them in place.