A Seasonal Pattern to New Generators Coming Online

Posted on the 08 March 2013 by Dailyfusion @dailyfusion
Source: U.S. Energy Information Administration

Source: U.S. Energy Information Administration

Statistical data published by the U.S. Energy Information Administration shows that utilities and other electric power plant developers usually start the operation of their new generation capacities at the start of summer or just before the New Year. For example, in December 2012, over 8 GW of new capacity came online. Between May, June, and July of 2013, power plant developers report they expect to bring approximately 5 GW of new capacity online.

A lot of power plants came into operation in December. This is especially true in case of wind power projects due to December often being the last month before an expected expiration of the federal wind production tax credit. Other power plant developers may also try to get their generators online before the end of the year because of different financial or tax purposes.

Source: U.S. Energy Information Administration, Form EIA-860 Annual Electric Generator Report, and Form EIA-860M (see Table ES3 in the January 2013 Electric Power Monthly)  Note: Data for 2012 are preliminary. Data include all operable U.S. generators, the oldest of which first came online in 1891 and the most recent in 2012. Retired generators are excluded. Data show capacity as reported during 2012; a generator's summer capacity is subject to change over time, for example, when the generator undergoes an uprate or derate.

Source: U.S. Energy Information Administration, Form EIA-860 Annual Electric Generator Report, and Form EIA-860M (see Table ES3 in the January 2013 Electric Power Monthly)
Note: Data for 2012 are preliminary. Data include all operable U.S. generators, the oldest of which first came online in 1891 and the most recent in 2012. Retired generators are excluded. Data show capacity as reported during 2012; a generator’s summer capacity is subject to change over time, for example, when the generator undergoes an uprate or derate.

Many other generators come online during the summertime, with June as a target month, to be available before the demand for electricity is at its highest level. Often, electric system planners require that a generator be online by June to be considered available to meet the system peak and to be counted in the reserve margin calculation. Finally, wholesale electric power prices tend to be higher in the summertime, so short-term profitability is higher for a generator coming online in June rather than in March.

This trend toward summer online dates is more pronounced for peaking generators, which operate only when electric demand is high, than for baseload generators, which operate more consistently. Taking natural gas-fired generators as an example (see chart below), the trend toward summer online dates is more pronounced for gas combustion turbines and combined-cycle units, which have historically operated as peaking or intermediate generators, than for baseload steam turbines.

These seasonal patterns hold regardless of the generator’s age because generating unit operators have been following this practice for decades.